Port of Dover Underwater Concrete Demolition Works

Topbond PLC

Dates:

June 2021

Related News

Coming Soon

Overview

Marine and Civil Diving Services Ltd were contracted by Topbond PLC on behalf of The Port of Dover to provide diving services for underwater concrete demolition works.

  • Work site access will be achieved from a man riding basket on quayside and Jack Up Barge
  • Diver to report back findings and Supervisor to submit report
  • Remove 3 x triangular concrete sections
  • Set up core drill frame and monitor core drill
  • Thread diamond wire through core holes

Other Projects

Fulham FC New Riverside Stand
Buckingham Group
Project Type: Construction

Project Duration: July 19 – March 22
READ MORE
Plaistow and Royal Primrose Wharves
Keltbray Ltd
Project Type: Construction

Project Duration: Nov 21 – May 22
READ MORE
Nearshore / Inland Warerways

Within Port of Dover

Subsea

Working at depths of 10m

Health and Safety

No accidents or incidents

Topbond PLC

Project Value:

Dates:

June 2021
PREVIOUS
Kingsferry Bridge Film Set
NEXT
Serpentine Outfall Inspection Works

Overview

Marine and Civil Diving Services Ltd were contracted by Topbond PLC on behalf of The Port of Dover to provide diving services for underwater concrete demolition works.

  • Work site access will be achieved from a man riding basket on quayside and Jack Up Barge
  • Diver to report back findings and Supervisor to submit report
  • Remove 3 x triangular concrete sections
  • Set up core drill frame and monitor core drill
  • Thread diamond wire through core holes
Nearshore / Inland Warerways

Within Port of Dover

Subsea

Working at depths of 10m

Health and Safety

No accidents or incidents